Important

The largest physically possible array does not always offer the shortest payback or the lowest risk. This guide covers decision-making questions only; obtain project-specific engineering, electrical and safety advice and confirm Irish law and SEAI conditions independently.

Should a warehouse cover its entire roof with solar panels?

Not automatically. Start with structurally usable roof area and the business's electricity use during daylight, then assess network connection and export terms. The best financial system size may be smaller than the maximum number of panels that fit.

What should you check?

An inactive warehouse with a large roof can have relatively little on-site demand. A refrigerated warehouse or busy distribution centre can have a very different load profile.

The proposal should compare several practical sizes, showing generation, expected self-consumption, grid export or curtailment, upfront cost and payback for each.

Allow for skylights, access routes, roof equipment, shading, fire and maintenance provisions, not just gross roof dimensions.

Ask the installer: Can you compare two or three system sizes and show the extra value of the final increment of panels?

What electricity data does a business need for an accurate commercial solar estimate?

At minimum, collect annual kWh use and tariff information; for a useful engineering forecast, interval-meter or half-hourly data is much better. This shows when electricity is actually used and how it overlaps with predicted solar production.

What should you check?

A yearly electricity bill cannot reveal the balance between daylight and night-time consumption or the effect of weekend shutdowns and operating shifts.

Also identify the appropriate MPRN, connection capacity, roof orientation and shading, planned new loads and any restrictions on export.

A credible installer should explain the software, weather and loss assumptions behind its annual generation forecast. Ask for outputs in kWh, not only a percentage of the electricity bill.

Ask the installer: Are your predicted self-consumption and payback based on our actual interval data and current tariff rather than a generic percentage?

How does a factory with night shifts calculate solar savings?

Separate daytime demand, when PV can generate, from night-time consumption, when standard solar panels cannot. High total annual factory electricity use does not guarantee high solar self-consumption if most processes run after dark.

What should you check?

Model the actual shift pattern for weekdays, weekends and seasonal production changes. Include process cooling or auxiliary equipment that may operate while the factory is otherwise closed.

Imported electricity avoided during daylight can be more valuable than exported surplus, but the actual comparison depends on the site's tariffs and export agreement.

Future load changes such as new equipment, increased electrification or EV charging should be calculated as scenarios rather than silently included in the current business case.

Ask the installer: What proportion of output is used during each shift, and how does the ROI change if production hours change?

Does a commercial solar project need a battery?

No, a battery is not automatically required. Its value depends on the cost of storage, available export arrangements, demand outside daylight hours and the exact electrical objectives, including whether approved backup power is needed.

What should you check?

A business with strong daytime consumption may use much of its PV output without a battery. A battery can alter the timing of consumption, but adds installation costs, losses, maintenance and equipment considerations.

Backup power is a different technical requirement from storing surplus solar generation; an ordinary battery-plus-PV quote does not automatically promise safe supply during outages.

Do not assume batteries are eligible under the solar PV portion of the SEAI NDMG scheme. Check the current invoice and eligible-cost definitions separately.

Ask the installer: Show me the financial forecast with and without storage, and specify if the battery offers approved backup/islanding.

Can a business sell excess solar electricity back to the grid?

Potentially, provided the installation has the appropriate connection and export arrangements. Export permissions, limits, metering and payment terms depend on the system and commercial agreements, so a fixed export price should never be assumed for every Irish business.

What should you check?

A system with approved export capability may receive value for surplus energy, but not every site can export freely at the capacity proposed.

A non-export or limited-export scheme may curtail generation when on-site demand is low, affecting annual yield and payback.

Ask for the export volume and price assumptions to be stated separately from savings from electricity used on site, and confirm actual agreements before making an investment decision.

Ask the installer: What export capacity is allowed, who pays for exported energy, and what happens to surplus production if the limit is reached?
How these answers were researched

Research checked 17 November 2026. Themes were drawn from UK commercial rooftop solar guidance and US Department of Energy materials, then adapted to Ireland using ESB Networks, HSA, SEAI and Irish government guidance. Foreign standards, permissions and safety distances are not presented as legally applicable in Ireland. These are editorially researched questions, not verified keyword search-volume figures or engineering approvals.

Questions to take to your next solar meeting

Start by asking for the site survey, design assumptions and connection route. Then compare supplier quotes on system size, works included, annual generation, maintenance and realistic self-consumption. The solar installer quotation brief builder produces a checklist you can copy without giving us your contact information.