What determines a business solar payback period?
The main factors are installation cost, grant eligibility, annual generation, electricity consumed on site, value of exported electricity and ongoing costs. A building with steady daytime demand may be able to use a larger share of generation directly. A building with little daytime demand may depend more heavily on export arrangements.
This is not the same as a discounted cash-flow return, and it does not show financing, tax or long-term equipment replacement costs.
A worked 30 kWp business solar example
This is an illustrative scenario using the example values from our calculator — not a researched national installation price or a prediction for any particular site.
| Input | Illustrative figure | What it means |
|---|---|---|
| System size | 30 kWp | Rated installed PV capacity |
| Eligible PV cost | €36,000 ex VAT | Hypothetical installation quotation |
| Annual generation | 850 kWh per kWp | Assumed production, not a roof-specific simulation |
| Used on site | 80% | Share that offsets imported electricity |
| Avoided import cost | €0.25 per kWh | Illustrative marginal tariff |
| Export value | €0.10 per kWh | Illustrative export rate |
| Annual maintenance | €350 | Hypothetical ongoing cost |
Step 1: Estimate electricity generated
30 kWp × 850 kWh per kWp = 25,500 kWh of estimated annual electricity generation. Actual output depends on location, roof angle, direction, shading, component performance and weather.
Step 2: Value electricity used on site
At 80% on-site consumption, 20,400 kWh is used by the business. At an assumed avoided import rate of €0.25/kWh, that is €5,100 per year of potential import-cost savings. The remaining 5,100 kWh at €0.10/kWh produces €510 in indicative export value.
Step 3: Allow for maintenance
€5,100 plus €510 export value, less €350 annual maintenance, gives €5,260 estimated annual net benefit. Fixed electricity standing charges are not treated as savings because installing PV does not necessarily remove them.
Step 4: Apply the SEAI grant schedule and cap
The enhanced 2026–2027 grant schedule has a nominal amount of €17,200 for 30 kWp. However, 45% of the example €36,000 eligible cost is €16,200. Under the published cost-cap rule the indicative grant in this scenario is therefore €16,200, not €17,200, assuming the applicant and installation qualify.
Step 5: Calculate simple payback
€36,000 minus €16,200 gives a hypothetical €19,800 net PV investment. Dividing this by €5,260 estimated annual net benefit gives approximately 3.8 years simple payback.
If only 40% of energy is used on site rather than 80%, the model assigns more generation the lower assumed export value. If the electricity tariff drops, annual savings fall; if roof generation or eligible costs change, so does payback. Test those scenarios instead of relying on a single optimistic result.
Why simple payback is not the whole financial case
It assumes constant production, prices and annual maintenance. A proper investment appraisal may also consider discount rate, inflation, tax treatment, financing interest, inverter replacement, degradation, export constraints and future on-site electricity demand. For a larger system, use interval-meter data and a qualified designer's generation model.
How should businesses compare installer ROI projections?
Ask each provider to show a separate line for generation, self-consumption, avoided energy price, export rate, maintenance, eligible grant amount and net capital cost. Ask whether their report includes VAT, connection upgrades, structural works and any battery system. Compare like-for-like assumptions before judging whose payback is shorter.
You can use our solar quote checklist tool to prepare the same brief for several installers, and the interactive solar ROI calculator to change assumptions yourself.
Grant source and review: SEAI Non-Domestic Microgen Scheme Application Guide v1.5, reviewed 17 November 2026. The enhanced grant window covers new applications from 6 October 2026 to 6 July 2027. Read the official application guide (PDF).