NDMG in 30 seconds

The scheme supports eligible solar PV capacity up to 1,000 kWp for self-consumption at qualifying non-domestic sites. Under the published enhanced window for new applications from 6 October 2026 to 6 July 2027, the band-based amount can reach €325,200, but actual payment is limited to the lower of the application amount or 45% of eligible invoiced installation cost. SEAI approval must come before works begin.

For the broader funding overview, see our commercial solar grants Ireland guide. For a numerical estimate, use the NDMG grant calculator.

What does “Non-Domestic Microgen” mean?

“Non-domestic” refers to eligible organisations and buildings outside an ordinary household solar project. “Microgen” is the shortened term used in the scheme name, but this grant can support much larger solar PV installations than most people associate with a small domestic array: the published grant schedule reaches 1 megawatt-peak (1,000 kWp).

It is administered by the Sustainable Energy Authority of Ireland (SEAI) under the government's Microgeneration Support Scheme. The purpose is to help qualifying sites generate electricity for their own operations. It is not the same as the domestic solar electricity grant, nor does it automatically pay for every energy-related item on a contractor's quotation.

Who qualifies for the Non-Domestic Microgen Grant?

The applicant's sector alone is not enough. SEAI assesses the applicant, premises, equipment, contractor and compliance with the scheme's rules. Use this practical eligibility checklist before asking an installer to prepare an application.

1. Eligible applicant

The scheme includes businesses, agricultural organisations, public bodies, schools, community groups and qualifying not-for-profits.

2. Qualifying premises

SEAI's September 2026 application guide requires the premises to have been built and occupied by 31 December 2024.

3. Electricity demand

The proposed installation must serve a site with electricity demand: it is not an export-only development grant.

4. Meter point

Support is normally available once per MPRN. A domestic MPRN supplying a registered business may qualify, subject to SEAI's requirements.

5. Registered professionals

Works must involve an appropriately SEAI-registered solar PV company and installer and compliant electrical works.

6. Grant offer first

Apply and receive a letter of offer before purchasing materials or starting the funded works.

Can a farmer apply for NDMG?

Yes, agriculture is an eligible sector, but a farm application still needs to meet building, ownership, financial, electrical and other conditions. If the relevant electricity supply uses a domestic MPRN, SEAI's guide allows an application where it supplies a registered business, subject to evidence and the other rules. Avoid assuming every farm building or farmhouse setup qualifies.

Are schools, community buildings and charities eligible?

SEAI includes schools, public bodies, community centres and non-profit organisations. Applicants should check which legal entity holds the contract and MPRN, how the organisation is funded, whether its building satisfies the occupancy cut-off and whether another source of State aid applies.

What about a rented warehouse or a business in a shared unit?

Begin with the building owner's permission, the organisation responsible for the MPRN, the roof's condition and the intended use of electricity. A tenant should obtain written clarity on access, ownership of the installation, maintenance, landlord consent and what happens at the end of a lease. The SEAI application requirements and contract should be reviewed for the specific arrangement rather than relying on the building's industry category.

How do the enhanced 2026–2027 grant rules work?

SEAI's September 2026 scheme guide sets out higher support for new applications made from 6 October 2026 to 6 July 2027. Existing applications do not automatically receive the uplift. A previous offer cannot simply be increased after installation has started.

The schedule is cumulative across capacity bands, not a single percentage applied to the quotation. For example, an eligible 30 kWp system has a published scheduled amount of €17,200 before applying the cost cap. If the eligible installation invoice is €36,000, the 45% cap would bring the indicative amount down to €16,200. Both are illustrative: SEAI makes the actual offer and payment decision.

Use the dedicated SEAI grant calculator to change the system size and eligible cost. Our solar ROI calculator adds estimated electricity savings and simple payback, which are separate questions from grant eligibility.

How do I apply for an SEAI NDMG grant?

1. Assess the site and obtain comparable quotes

Document the annual electricity demand, roof or land constraints, electrical connection and potential PV size. Compare quotes from registered Non-Domestic Microgen solar PV companies on the same scope, including installation, grid obligations and aftercare.

2. Appoint a registered company and agree the proposed works

SEAI's process requires choosing a registered company and agreeing the contract before submitting the application. That is different from starting construction: the grant letter must come first.

3. Apply through SEAI and wait for the offer

Submit the information requested in the official online process. Do not order the funded materials or begin the grant-supported works before the required approval. Published grant offers normally last eight months.

4. Arrange the ESB Networks requirements

The appropriate notification or application depends on the project. The installer should explain which network process applies, the evidence required and whether there are connection works or witness tests to schedule.

5. Install and provide completion evidence

After approval and required network steps, the registered installer completes and signs the works documentation. The applicant and installer provide invoices and other supporting records required for inspection and payment.

Important: A submission or quote is not a grant award. The authoritative application steps, supporting documents and current availability are on SEAI's official scheme page.

What documents should you prepare?

The exact application package depends on the applicant and project. Businesses should be ready to clarify the registered applicant, business and site address, MPRN, historical building occupancy, suitable registered installer, system capacity, contracts and costs. They may also need proof relating to the grid connection, financial standing, State aid, landlord permissions, and tax compliance.

For a useful first conversation with suppliers, gather a recent electricity bill and a year of consumption data if available; photographs or drawings of the roof; the age, material and condition of the roof; and any known electrical upgrades. The commercial solar quote brief can help you ask each installer for the same information.

Which costs can count towards the grant?

The enhanced schedule concerns the qualifying solar PV installation. SEAI's guide distinguishes eligible installation work from batteries and supplementary elements outside the standard PV system. Itemised quotes should show those separately. The State-aid ceiling is assessed against qualifying installation expenditure, and other State funding can affect what is payable. VAT and the treatment of particular invoice items should be checked against the current scheme documentation and your professional advisers.

The grant ceiling should not be confused with project payback. A larger grant does not necessarily make the biggest possible array the right option: on-site consumption, export limitations, roof engineering and operating hours still matter. See our commercial solar payback guide for the investment side.

Frequently asked NDMG questions

Does the scheme require a BER certificate?

SEAI's September 2026 application guide says applicants are not required to have an existing Building Energy Rating certificate or obtain one after the supported solar PV work. Other building and installation standards still apply.

Can I get a grant for an export-only solar development?

The NDMG guide states that supported sites must have their own electricity demand. It is not designed for grid-connected developments whose only purpose is exporting electricity. Export arrangements may still form part of a self-consumption project.

Can I combine NDMG with another government grant?

Do not assume grants can be stacked. The official guide includes rules about other State funding for the same installation and the overall aid-intensity ceiling. Check the precise combination with SEAI before proceeding.

Is SEAI's approval guaranteed if my project is under 1,000 kWp?

No. Capacity is just one part of eligibility. A compliant site, a registered installer, correct application timing and the programme's technical, financial and State-aid conditions still need to be satisfied.

Official sources and independence: This is an independent guide, not SEAI advice or a government application portal. Consult SEAI's Non-Domestic Microgen Scheme Application Guide (v1.5) and the live SEAI scheme page; both take precedence if details change. Content reviewed 17 November 2026.